What goes in the internal job cost
Everything the job takes out of the business. If you are unsure whether a line belongs here, it does.
| Cost line | What to include |
|---|---|
| Materials | Merchant cost plus the waste you expect on pipe and fittings. Not the selling value. |
| Labour | Hours at what they cost the business, not the customer rate. |
| Other direct costs | Parking, clean-air charges, waste disposal, hire, notification fees. |
| Subcontractors | What the electrician, plasterer or tiler charges you. |
| Overhead | A share of van, insurance, tools, phone and accountant, usually a percentage of direct cost. |
None of these appear on the customer PDF. The hourly rate calculator turns overhead into a per-hour figure; the quote profit calculator applies it to a single job.
What goes on the customer quote
The selling price is what you ask the customer to pay before tax: material selling values, labour at the customer rate, charges you pass on, call-out and any uplift, after discount. Show it as one figure, as groups of work, or as lines with selling prices that add up to the quoted total. Then VAT if you charge it, the total, deposit and balance. The plumbing quote checklist covers the rest.
Why the customer PDF never shows cost or margin
A quote is a price for an outcome. The moment it shows what the boiler cost you, the conversation changes from “is this the right price for the job?” to “why are you charging £300 more than the price online?”. Your margin pays for the van, insurance, callbacks and unpaid quoting; the customer is not buying those lines. If they ask for a breakdown, show selling prices by line or group, adding up to the same total.
Worked example: from a £1,240 cost to a price with VAT
Illustrative figures chosen to show the maths, not a price guide.
A one-day job to replace a kitchen sink, mixer tap and waste, with a short run of new pipework and an electrician to move a socket.
| Internal cost line | £ |
|---|---|
| Materials including waste | £605.00 |
| Labour, 15 hours at £28.00 internal cost | £420.00 |
| Parking | £25.00 |
| Disposal of the old sink and offcuts | £35.00 |
| Electrician, socket move | £40.00 |
| Direct cost | £1,125.00 |
| Overhead share, just over 10% of direct cost | £115.00 |
| Job cost | £1,240.00 |
You want to keep a 30% margin. Divide the cost by one minus the margin: £1,240.00 ÷ 0.70 =£1,771.43 ex VAT. Add 20% VAT of £354.29 and the customer total is £2,125.71.
The profit is £531.43: 30% of the price and 42.9% of the cost. Had you added 30% to the cost instead, the price would have been £1,612.00, the profit £372.00 and the margin only 23.1%. The margin vs markup calculator shows that gap for any percentage.
What the customer sees: “Replace kitchen sink, mixer tap and waste, including new pipework and relocation of one socket by a qualified electrician. Subtotal £1,771.43. VAT £354.29. Total £2,125.71.”
Common leaks between cost and price
- Waste. Pipe is bought in 3-metre lengths and used in 1.4-metre runs; five per cent on pipe and fittings is normal.
- Return visits. Commissioning, the part on back-order, the snag. One unpriced return visit on a £400 job removes most of the margin.
- Unpriced making-good. Boxing in, filling, a tile or two. If it is not in the scope, it goes in the exclusions. If it is in neither, you are doing it free.
- The customer rate used as the cost. Put £65 an hour in the cost column and labour shows no margin, so you under-price every other line to compensate.
Finish the cost before you read the price. Check a simple job here, then build the real quote in the app, where the customer copy and the internal copy stay apart. If you charge VAT, add it last with the VAT calculator.
Frequently asked questions
What is the difference between job cost and selling price?
Job cost is what the work costs your business: materials including waste, your hours at what they cost you, parking, disposal, hire, subcontractors and a share of overhead. Selling price is what you ask the customer to pay before VAT. The gap is your gross profit, and that gap divided by the selling price is your margin.
Should I show my hourly rate on a plumbing quote?
You can, but you do not have to. Many plumbers quote a fixed price for a described scope. If you do show a rate, show the customer rate, never the internal cost.
How do I turn a job cost into a selling price?
Divide the cost by one minus the margin you want. For a 30% margin on a £1,240 cost: £1,240 ÷ 0.70 = £1,771.43 before VAT. Multiplying by 1.30 gives £1,612, which is a 30% markup but only a 23.1% margin. Add VAT last if you are registered.
Keep cost and price apart on every quote
Cost the job, check the margin, send a PDF. 3 quotes free. Then £5/month or £50/year. Cancel anytime.
No card. No account.